On-site activity is minimal. Tuesday the mastic between pool deck and coping was installed. Wednesday the anchors for the spa cover were installed, but a section of the coping broke free. Thursday the broken section was repaired, some minor mortar cavities were filled, and a gap in the driveway (where an irrigation pipe was laid) was filled. Friday the loose/broken paving stones were fixed. About the only outstanding issues from the original contract are:
- Add rain downspout to section of new roof (sub-contractor)
- check on a spot that seems to be always wet.
I mowed the lawn Friday. Most of the garden furniture we’ve ordered has arrived. This weekend I’m going to try to finish oiling the un-oiled wood bits.
That’s all for this story.