Oct 16-20, 2000
Insulation and wall board go up this week. The wet area held water without a leak from Friday until they drained in Wednesday. And speaking of leaks I fixed the leak in the downstairs bathroom – it was a leaking wax seal under the toilet exacerbated by lots of silicon sealer around the bowl keeping the leak hidden until it worked its way under the tile to the wall.
More wall board. All seems to be done save the odd size sections above the triangular soffit. The inspector was here and signed off on both the wallboard and the shower pan.
The final bits of sheet-rock were done and we’re now ready for the taper to come in next week and make it look pretty.