Oct 20-Nov 3, 2000
More taping this week. Monday a second coat of mud went on; Wednesday a third. Friday they’ll be back to do some sanding.
The taper’s finished his job. The stone fabricators were here to take their first (rough) measurements and detailed notes. The wet area walls and floor will need to be floated (a layer of mud added to prepare surfaces for the stone). The person who will do that job was also here to sync with the fabricators as to where joints will go for proper sloping/drainage, etc. Of course they are all very busy. They’ll let the contractor know schedules, later.