Jan 15-19, 2001
The remainder of the plumbing fixtures we ordered have arrived. There’s still a slight issue regarding the handles, but that will be resolved later. A sample of the honed stone for the floors and the cutting pattern were approved. More stone was obtained (10 slabs were not enough so 5 more were ordered). The sample we were shown of the new slabs match the installed stone quite well. Hopefully the installation will continue next week. The metal bits are being fabricated and plated.