Mar 19-23, 2001
The stone fab guys showed up a little after 8:00 AM on Tuesday to get the remaining stone bits in – at least enough to let the other trades do their things. That primarily meant the wash basins and the toilet room floor. You might notice in the 2nd picture that one of the was basins looks like its slightly twisted in a clockwise direction. Will ask the contractor what can be done about that.
The stone baseboard trim in the toilet room stick out 1/2 inch to allow for the cedar cladding. There are seams in the steam room that need some work, too. Wednesday I’ll find out when the plumbers can install the toilet and get us some running water.
At 7:30 this morning the plumbers started installation of showers, sinks, and toilet. The faucet handles are not correct and will change. The handle were not installed on the showers as we don’t need them yet. It’s nice to have a working toilet upstairs, even if there is no power in that room, yet.