Waiting for plaster to dry (Sep 1-5)
This is a short week. The taper has been in most every day, applying a bit more plaster then letting it dry over night before applying the next coat. The electician finished his work Thursday. The wallboard seams were sanded Friday morning. The carpenters then restored all trim in the office and bathroom. The toilet was put back in the bathroom along with the medicine cabinet and lights. The office is ready to paint. We met with the painter Thursday to select colors.
taped seams in office
taped seams in bathroom
toilet installed
medicine cabinet/lights