Monday–Wednesday, 12–14 Sep 2022
UV protectant applied
Strapped to stand-offs
Lines covered
The first coat of UV proctant was applied before the power/control line was put in place. Then a second coat of UV protectant was added and all lines were strapped to stand offs. The lines runing down the wall were covered after some expanding foam used where the lines enter the house.
drain to downspout
gap filler
The drain line from the upstairs unit was extended and routed to the nearest roof downspout. Standoffs will be added to slightly raise the line from the room. Expanding foam was also added where the lines enter the house for the downstairs unit.
Heat pump anchored to pad
Drain termination
Mostly tidy
More clean-up. The heat pump is anchored to its pad and the lines leading to the heat pump have been tidied. Caulk has been applied where various lines exit the house. Small stand-offs have been caulked to the upstairs drain pipe, too. Most everything is done.
Thursday, 15 Sep 2022
Insulated lines
more insulated lines
caulked
That’s it. The last bit of bare copper tubing has been insulated and some caulk added around the inside access hole for the upstairs unit. I’ve started putting the things I moved out of the way back where they belong.
On to the next household project: our pool needs some love.